Flagship first project for CPC 2013
NB This article was written in February 2015. In November 2015, the Complex Projects Contract was updated and renamed the Time and cost management contract TCM15.
The Complex Projects Contract (CPC 2013) was developed by the Chartered Institute of Building (CIOB). Launched on 23 April 2013, it is thought to be the world’s first contract specifically aimed at the management of time in complex construction and engineering projects.
The first project to use CPC 13 looks set to be the £600M United Nations (UN) headquarters in Geneva, the Palais des Nations, which is a complex, overlapping, phased new build and refurbishment project. The UN has already decided to adopt the proposed CPC consultancy document for its professional appointments prior to the document’s formal publication. Construction of the six year building programme is due to start in 2017.
The intention is to use the CIOB Contract Agreement with 90% of its clauses un-amended. It will be interesting to examine which clauses the employer’s team consider need alteration. The conditions of contract and appendices which are project specific will have to be prepared by the consultant team. The independent 'valuer' and the 'project time manager' have yet to be appointed by the employer. These key appointments will be fundamental to the success of this first test of a new way of working. The two explanatory documents accompanying the contract 'user notes' and 'general index' will also be put to the test although neither document is contractual.
In some aspects CPC 2013 takes its lead from the New Engineering Contract (NEC) insomuch as it is:
- Written in plain English with practical engineering, project management and cost consultancy input to the legal drafting.
- It encourages parties to put more effort into defining the programme and pricing risk.
- It is versatile, suitable for use with; measured work, fixed price, design and build, target cost or traditional procurement systems.
- It promotes transparency and collaboration.
- It empowers the employer to manage its risks.
- It aims to anticipate adverse time or cost issues with early warnings.
- It provides for quick and inexpensive dispute resolution.
However, CPC 2013 seeks to improve on the NEC provisions by introducing management protocols and mechanisms using activity-based pricing and synchronised work schedules which include the pricing of time contingencies. This requires a critical path programme setting out free float for each activity as well as total float. The project programme has three levels of density to ensure it remains dynamic:
- Low density which sets out programmed work for 10 months and beyond.
- Medium density for work from 4 to 9 moths.
- High density which is short term.
This process sets out to constantly predict the outcome of costs and completion. The latest updated position is published electronically and collaborative meetings are held to do whatever is practical to reduce delays and unforeseen costs. The contract administrator can instruct remedial measures accordingly. Liquidated and ascertained damages as well as capped consequential losses can be levied for delays caused by matters under the contractor’s control.
CPC 13 seeks to clearly address and allocate risk and its adverse costs. It is very thorough in setting out how timescales are to be predicted and monitored, including contingency planning. The contract addresses concurrent delay in relation to extension of time and financial entitlement.
The independent valuer, who assesses interim payments for work, assisted by transparency of time and priced contingency (set out in the contract and as work proceeds) has more tools at their disposal to assess costs of delay, particularly when building information modelling (BIM) data is synchronised with work schedules. These arrangements should lead to better control of variations than has been the case with NEC projects.
In an effort to prevent festering disputes there is a fast and relatively cheap adjudication procedure which can be invoked when parties cannot reach agreement. Outside experts can be brought in to assist the adjudicator’s determination which is binding if not challenged within 20 working days.
The eyes of the industry will be focused on the Geneva project which will doubtless reveal teething problems leading to improvements.
--CIOB
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- BIM.
- CIOB.
- Collaborative practices.
- Construction contract.
- CPC 2013.
- Critical path.
- FIDIC.
- JCT.
- NEC3.
- Procurement route.
- Project programme.
[edit] External references
- Construction Manager February 2015 edition
- Contracts and Law by Keith Pickavance
- CIOB WEBSITE – CPC 13 Webinar
Featured articles and news
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.
Drone data at the edge: three steps to better AI insights
Offering greater accuracy and quicker access to insights.
From fit-out to higher-risk buildings.
Heritage conservation in Calgary
The triple bottom line.
College of West Anglia apprentice wins SkillELECTRIC gold.
Scottish government launch delivery plan
To strengthen planning and tackle the housing emergency.
How people react in ways which tend to restore their comfort.
Comfort is a crucial missing piece of the puzzle.
ECA launches Recharging Electrical Skills Charter in Wales
Best solutions for the industry and electrical skills in Wales.
New homebuilding skills hub launch and industry response
Working with CITB and NHBC to launch fast track training.